Greenway Extension Project - Project Timeline & Updates

Target Dates For Key Project Stages

Design Phase Complete:       2nd Quarter 2019

Right-Of-Way Acquisition:     4th Quarter 2019

Construction Start:                 1st Quarter 2020

Public Use By:                         3rd Quarter 2021

Total Project Completion:      4th Quarter 2021

 

Project Updates

Follow this blog for the latest information on the project.  Updates will be posted monthly, at a minimum, as well as when there are significant developments of interest to the public.


Project Updates:


Construction will begin!

by Krista McDowell | Feb 04, 2020

Construction on the Greenway Extension will begin soon! A notice to proceed will be issued within the next week or two! Construction is expected to begin along Marconi and proceed northward. The expected completion of this construction is anticipated to be early Summer 2021.