Greenway Extension Project - Project Timeline & Updates

Target Dates For Key Project Stages

Design Phase Complete:       2nd Quarter 2019

Right-Of-Way Acquisition:     4th Quarter 2019

Construction Start:                 1st Quarter 2020

Public Use By:                         3rd Quarter 2021

Total Project Completion:      4th Quarter 2021

 

Project Updates

Follow this blog for the latest information on the project.  Updates will be posted monthly, at a minimum, as well as when there are significant developments of interest to the public.


Project Updates:


Tunnel Installation- June 2020

by Krista McDowell | Jun 04, 2020

During the past month, the contractor has been grading the trail area north of Windward Parkway and along Marconi Drive and has completed installation of helical piers, which are used to provide foundational support for structures for three boardwalk sections.  Additionally, preparatory work for the installation of the tunnel under Windward Parkway has begun and traffic flow along that stretch of Windward Parkway has been modified accordingly.  Upcoming work will include continued construction of the tunnel under Windward Parkway, construction of retaining walls, continuation of boardwalk construction, and grading along Marconi Drive and north of Windward Parkway.

We will keep you updated monthly on this project with key milestones.