Greenway Extension Project - Project Timeline & Updates

Target Dates For Key Project Stages

Design Phase Complete:       2nd Quarter 2019

Right-Of-Way Acquisition:     4th Quarter 2019

Construction Start:                 1st Quarter 2020

Public Use By:                         3rd Quarter 2021

Total Project Completion:      4th Quarter 2021

 

Project Updates

Follow this blog for the latest information on the project.  Updates will be posted monthly, at a minimum, as well as when there are significant developments of interest to the public.


Project Updates:


  • Traffic Flow Changes - May 2020

    by Krista McDowell | May 11, 2020

    During the past month, clearing of the trail alignment has continued and the contractor has installed approximately 350 feet of storm drainage near the tunnel location. Additionally, the construction of two boardwalk sections have begun with the installation of helical piers, which are used to provide foundational support for structures.  Upcoming work will include construction of retaining walls, beginning the installation of the tunnel crossing under Windward Parkway, additional storm drainage installation, continuation of boardwalk construction, and grading along Marconi Drive. Beginning May 15th, traffic patterns along Windward Parkway, between Union Hill Road/Market Place and Compass Pointe Crossing, will change to permit the beginning of construction of the tunnel under Windward Parkway. As they install each half of the tunnel, they will close off both lanes of traffic in one direction. The other side of the road will then be utilized to provide one lane of travel in each direction. The two lanes from Union Hill Road/Market Place towards Compass Pointe Crossing will be closed and the two lanes headed from Compass Pointe Crossing toward Union Hill Road/Market Place will be utilized to provide on lane in each direction. When they complete the first half of the tunnel, they will then flip the traffic flow. Traffic delays due to construction should be expected.

    We will keep you updated monthly on this project with key milestones.

  • Progress- April 2020

    by Krista McDowell | Apr 09, 2020

    The contractor has installed over 1,000 feet of trail along Windward Parkway and Union Hill Road, cleared approximately an additional 1,000 feet of trail, and has begun installation of storm drainage along Windward Parkway between Market Place/Union Hill Road and Big Creek.  Upcoming activities will include: continued clearing and installation of erosion control measures, continued placement of trail along Windward Parkway and Marconi Drive, continued installation of storm drainage, and start of retaining wall construction.

    We will keep you updated monthly on this project with key milestones.

  • Erosion Control - March 5, 2020

    by Krista McDowell | Mar 05, 2020
    The contractor has begun work beginning along Windward Parkway, between Marconi Drive and Windward Plaza. Currently, installation of erosion control measures and tree clearing is expected to progress down Marconi Drive towards the existing Greenway Trail head this month.

    Work of the same nature is also anticipated to occur on along Windward Parkway between Market Place/Union Hill Road and Big Creek.  Additionally, the contractor hopes to begin installation of storm drainage to the south of Windward Parkway in this area, weather permitting. The next task in the project would be to begin work on curb and gutter near the entrance to Union Hill Park. 

    We will keep you updated monthly on this project with key milestones

  • Notice to Proceed - February 10, 2020

    by Krista McDowell | Feb 07, 2020
    The Notice to Proceed has been issued for Monday, February, 10th. However, due to all of the rain, construction may be delayed until the following week. Work is projected to start at the pedestrian bridge at Camp Creek and Windward Parkway.

    We will keep you updated monthly on this project with key milestones. 
  • Construction will begin!

    by Krista McDowell | Feb 04, 2020

    Construction on the Greenway Extension will begin soon! A notice to proceed will be issued within the next week or two! Construction is expected to begin along Marconi and proceed northward. The expected completion of this construction is anticipated to be early Summer 2021.