Design Phase Complete: 4th Quarter 2018
Right-Of-Way Acquisition: 4th Quarter 2019
Construction Start: 1st Quarter 2020
Public Use By: 2nd Quarter 2021
Total Project Completion: 3rd Quarter 2021
Project Updates
Follow this blog for the latest information on the project. Updates will be posted monthly, at a minimum, as well as when there are significant developments of interest to the public.
Progress is underway- April 2020
by
Krista McDowell
| Apr 08, 2020
Things are moving along on this project. Erosion control installation and tree clearing is complete. The storm drainage installation and grading has started and is ongoing. Fulton County Waterline installation is anticipated to begin during the week of April 14th. Heavy traffic delays due to construction should be expected.
We will keep you updated monthly on this project with key milestones.