Kimball Bridge Road - Phase 1- Project Timeline & Updates

Target Dates For Key Project Stages

Design Phase Complete:       4th Quarter 2018

Right-Of-Way Acquisition:     4th Quarter 2019

Construction Start:                 1st Quarter 2020

Public Use By:                         2nd Quarter 2021

Total Project Completion:      3rd Quarter 2021

 

Project Updates

Follow this blog for the latest information on the project.  Updates will be posted monthly, at a minimum, as well as when there are significant developments of interest to the public.


Project Updates:

Waterline Installation almost complete - July 2020

by Krista McDowell | Jul 13, 2020
Storm drainage installation and grading is ongoing.  Georgia Power, Atlanta Gas Light and AT&T utility re-locations are ongoing.  The jack and bore (Jack and bore is a method of horizontal boring sewer construction. Construction crews drill a hole underground horizontally between two points without disturbing the surface between sending and receiving pits.) under North Point Parkway is complete, the 54” waterline installation under North Point Parkway is ongoing and is anticipated to be completed on 7/17/20.  Construction of Wall #6 in front of Fire Station #86 is ongoing.  The stone base for road widening from Waters Road to Saehan Church is installed.  Curb and gutter installation from Waters Road to Saehan Church is ongoing.

Heavy traffic delays due to construction should continue to be expected. 

We will keep you updated monthly on this project with key milestones.