Kimball Bridge Road - Phase 1- Project Timeline & Updates

Target Dates For Key Project Stages

Design Phase Complete:       4th Quarter 2018

Right-Of-Way Acquisition:     4th Quarter 2019

Construction Start:                 1st Quarter 2020

Public Use By:                         2nd Quarter 2021

Total Project Completion:      3rd Quarter 2021

 

Project Updates

Follow this blog for the latest information on the project.  Updates will be posted monthly, at a minimum, as well as when there are significant developments of interest to the public.


Project Updates:

Progress Update - August 2020

by Krista McDowell | Aug 11, 2020

 The 54” waterline installation under North Point Parkway is complete.  The installation of the 54” waterline from Big Creek heading towards Rock Mill Road has started and is ongoing.  Construction of wall #6 in front of Fire Station 86 is complete, except for the brick facing.  Curb and gutter installation between Waters Road and Rock Mill Road is ongoing.  Construction of wall 5 has started and is ongoing. Storm drainage installation and grading is ongoing.  Georgia Power, AT&T and Atlanta Gas Light utility re-locations are ongoing. 

Heavy traffic delays due to construction should continue to be expected.  

We will keep you updated monthly on this project with key milestones.