Design Phase Complete: 4th Quarter 2018
Right-Of-Way Acquisition: 4th Quarter 2019
Construction Start: 1st Quarter 2020
Public Use By: 2nd Quarter 2021
Total Project Completion: 3rd Quarter 2021
Project Updates
Follow this blog for the latest information on the project. Updates will be posted monthly, at a minimum, as well as when there are significant developments of interest to the public.
Progress Update - August 2020
by
Krista McDowell
| Aug 11, 2020
The 54” waterline installation under North Point Parkway is complete. The installation of the 54” waterline from Big Creek heading towards Rock Mill Road has started and is ongoing. Construction of wall #6 in front of Fire Station 86 is complete, except for the brick facing. Curb and gutter installation between Waters Road and Rock Mill Road is ongoing. Construction of wall 5 has started and is ongoing. Storm drainage installation and grading is ongoing. Georgia Power, AT&T and Atlanta Gas Light utility re-locations are ongoing.
Heavy traffic delays due to construction should continue to be expected.
We will keep you updated monthly on this project with key milestones.