Kimball Bridge Road - Phase 1- Project Timeline & Updates

Target Dates For Key Project Stages

Design Phase Complete:       4th Quarter 2018

Right-Of-Way Acquisition:     4th Quarter 2019

Construction Start:                 1st Quarter 2020

Public Use By:                         2nd Quarter 2021

Total Project Completion:      3rd Quarter 2021

 

Project Updates

Follow this blog for the latest information on the project.  Updates will be posted monthly, at a minimum, as well as when there are significant developments of interest to the public.


Project Updates:

Progress Update - September 2020

by Krista McDowell | Sep 10, 2020

The installation of the 54” waterline from Big Creek heading towards Rock Mill Road is ongoing and is anticipated to be complete at the end of September.  Curb and gutter installation between Waters Road and Rock Mill Road is ongoing.  Construction of wall 5, between Fire Station 86 and Big Creek, is ongoing.  Construction of wall 8, near the intersection of Kimball Bridge and Waters Road, has begun. Storm drainage installation and grading is ongoing.  Georgia Power, AT&T and Atlanta Gas Light utility re-locations are ongoing. 


Heavy traffic delays due to construction should continue to be expected.  

We will keep you updated monthly on this project with key milestones.