Kimball Bridge Road - Phase 1- Project Timeline & Updates

Target Dates For Key Project Stages

Design Phase Complete:       4th Quarter 2018

Right-Of-Way Acquisition:     4th Quarter 2019

Construction Start:                 1st Quarter 2020

Public Use By:                         2nd Quarter 2021

Total Project Completion:      3rd Quarter 2021

 

Project Updates

Follow this blog for the latest information on the project.  Updates will be posted monthly, at a minimum, as well as when there are significant developments of interest to the public.


Project Updates:

Progress Update - October 2020

by Krista McDowell | Oct 07, 2020

The installation of the 54” water main from Big Creek to North Point Parkway is complete.  The installation of the 54” water main from the west side of North Point Parkway to GA 400 is ongoing.  Curb and gutter installation and sidewalk installation between Waters Road and Big Creek are ongoing.  The construction of wall 5, between Fire Station 86 and Big Creek, is complete.  The installation of the brick veneer on wall 6, in front of Fire Station 86, has started and is ongoing.  Construction of wall, near the intersection of Waters Road, is ongoing.  

Storm drainage installation and grading is ongoing.  Georgia Power, AT&T and Atlanta Gas Light utility re-locations are ongoing. 


Heavy traffic delays due to construction should continue to be expected.  

We will keep you updated monthly on this project with key milestones.