Design Phase Complete: 4th Quarter 2018
Right-Of-Way Acquisition: 4th Quarter 2019
Construction Start: 1st Quarter 2020
Public Use By: 2nd Quarter 2021
Total Project Completion: 3rd Quarter 2021
Project Updates
Follow this blog for the latest information on the project. Updates will be posted monthly, at a minimum, as well as when there are significant developments of interest to the public.
Progress Update - October 2020
by
Krista McDowell
| Oct 07, 2020
The installation of the 54” water main from Big Creek to North Point Parkway is complete. The installation of the 54” water main from the west side of North Point Parkway to GA 400 is ongoing. Curb and gutter installation and sidewalk installation between Waters Road and Big Creek are ongoing. The construction of wall 5, between Fire Station 86 and Big Creek, is complete. The installation of the brick veneer on wall 6, in front of Fire Station 86, has started and is ongoing. Construction of wall, near the intersection of Waters Road, is ongoing.
Storm drainage installation and grading is ongoing. Georgia Power, AT&T and Atlanta Gas Light utility re-locations are ongoing.
Heavy traffic delays due to construction should continue to be expected.
We will keep you updated monthly on this project with key milestones.