by
Krista McDowell
| Dec 09, 2020
The installation of the 54” water main from the west side of North Point Parkway to GA 400 is complete. Curb and gutter installation and sidewalk installation between Waters Road and Big Creek are ongoing. The installation of brick veneer on wall 6, in front of Fire Station 86 is complete. The stone veneer installation on wall 5, between Fire Station 86 and Big Creek, has started and is ongoing. Construction of wall 8, near the intersection of Waters Road, is complete; except for the stone veneer. Construction of retaining walls 2 and 3, on both sides of the Rock Mill Park entrance, are complete; except for the veneer. The construction of wall 9, between Big Creek and Rock Mill Road, has started and is ongoing. Road widening construction on the North side of Kimball Bridge Road from Rock Mill Park to North Point Parkway has started and is ongoing.
Storm drainage installation and grading is ongoing.
Heavy traffic delays due to construction should continue to be expected.
We will keep you updated monthly on this project with key milestones.