by
Krista McDowell
| Apr 14, 2021
Recently, the stone veneer on wall 8, near the intersection of Waters Road, and construction of retaining wall 6, adjacent to Fire Station 86, has been completed. The 54" water main installation from Rock Mill Road to North Point Parkway has also been completed.
Currently, utility relocations, storm drainage installation, conduit for traffic signal interconnect and lighting are ongoing. Light poles and light fixtures are being installed. The construction of wall 7, between Fire Station 86 and Saehan Church, is ongoing. And, asphalt leveling at the roundabout and throughout Kimball Bridge Road continue.
Upcoming work will include the completion of the Greenway tie in to Sterling Brooke Subdivision. The completion of construction on retaining wall 9, at Greenway tie in on the west side of the bridge.
Heavy traffic delays due to construction should continue to be expected.
We will keep you updated monthly on this project with key milestones.