Kimball Bridge Road - Phase 1- Project Timeline & Updates

Target Dates For Key Project Stages

Design Phase Complete:       4th Quarter 2018

Right-Of-Way Acquisition:     4th Quarter 2019

Construction Start:                 1st Quarter 2020

Public Use By:                         2nd Quarter 2021

Total Project Completion:      3rd Quarter 2021

 

Project Updates

Follow this blog for the latest information on the project.  Updates will be posted monthly, at a minimum, as well as when there are significant developments of interest to the public.


Project Updates:

Progress Update- June 2021

by Krista McDowell | Jun 16, 2021
Recently, Wall 1 installation on the east side of Kimball Bridge Road just south of North Point Parkway was completed, Wall 9 installation complete at greenway tie in on west side of bridge, Guardrail installation is complete. The traffic shift to roundabout configuration is complete at Kimball Bridge Road and Rock Mill Road intersection.

Currently, utility relocations, storm drain installation, grading, sidewalk installation, curb and gutter installation is ongoing, pedestrian light poles and pedestrian light fixture installation, conduit installation for traffic signal interconnect and lighting continues, signal installation at the intersection of North Point Parkway and Kimball Bridge Road is ongoing, splitter island installation, median installation, road widening at North Point Parkway, stone veneer installation on wall 7 parapet between Fire Station #86 and Saehan Church, and asphalt paving is ongoing.

Upcoming work includes, the completion of wall 7 parapet stone veneer between Fire Station #86 and Saehan Church, the completion of wall 1 stone veneer on east side of Kimball Bridge Road just south of North Point Parkway, completion of stone veneer on wall 4 at New Prospect Elementary School corner of roundabout. Complete installation of splitter islands at roundabout, complete median installation, complete roundabout truck apron. Complete Greenway tie in to Sterling Brooke Subdivision, and the completion of the Greenway tie in at wall 9 on the west side of the bridge.