Design Phase Complete: 4th Quarter 2018
Right-Of-Way Acquisition: 4th Quarter 2019
Construction Start: 1st Quarter 2020
Public Use By: 2nd Quarter 2021
Total Project Completion: 3rd Quarter 2021
Project Updates
Follow this blog for the latest information on the project. Updates will be posted monthly, at a minimum, as well as when there are significant developments of interest to the public.
Progress Update- August 2021
by
Krista McDowell
| Oct 05, 2021
Roundabout completed and operational on August 4th. Milling and resurfacing of Sheridan Ridge Court completed on August 18th. Asphalt surface course complete from roundabout splitter island on North Point Parkway approach to bridge over Big Creek. Asphalt surface course complete at Rock Mill Park connection to roundabout. Asphalt surface course complete at New Prospect Elementary approach to roundabout. Sundance Academy driveway apron and asphalt tie in complete.
Upcoming work includes the completion of asphalt surface course and completion of the Greenway tie in to Sterling Brooke Subdivision.
Heavy traffic delays due to construction should continue to be expected. We will keep you updated on this project with key milestones.