by
Krista McDowell
| Oct 05, 2021
Current activity includes utility relocation, grading, sidewalk installation, curb and gutter installation, pedestrian light poles and light fixture installation, conduit installation for traffic signal interconnect and lighting, traffic signal installation at the intersection of North Point Parkway and Kimball Bridge Road, permanent signage installation, fine grading and permanent grassing. Asphalt surface course has been completed from Waters Road to bridge over Big Creek. The driveway apron installation has been completed at Collingwood Apartments.
Upcoming work includes to finish the Greenway tie ins and the final asphalt surface course installation from roundabout to project limits on the west side of North Point Parkway. The medians and islands will have topsoil and mulch installed.
Heavy traffic delays due to construction should continue to be expected. We will keep you updated on this project with key milestones.